October 2001
Ciba Geigy Consent Decree
XI. EPA APPROVAL OF PLANS AND OTHER SUBMISSIONS
37. After review of any plan, report or other item which is required to be submitted for approval pursuant to this Consent Decree, EPA, shall: (a) approve, in whole or in part, the submission; (b) approve the submission upon specified conditions; (c) modify the submission to cure the deficiencies; (d) disapprove, in whole or in part, the submission, directing that the Settling Defendants modify the submission; or (e) any combination of the above. However, EPA shall not modify a submission without first providing Settling Defendants at least one notice of deficiency and an opportunity to cure within 21 days, or a longer time as specified by EPA's Project Coordinator, except where to do so would cause serious disruption to the Work or where previous submission(s) have been disapproved due to material defects and the deficiencies in the submission under consideration indicate a bad faith lack of effort to submit an acceptable deliverable.
38. In the event of approval, approval upon conditions, or modification by EPA, pursuant to Paragraph 37(a), (b), or (c), Settling Defendants shall proceed to take any action required by the plan, report, or other item, as approved or modified by EPA subject only to their right to invoke the Dispute Resolution procedures set forth in Section XIX (Dispute Resolution) with respect to the modifications or conditions made by EPA. In the event that EPA modifies the submission to cure the deficiencies pursuant to Paragraph 37(c) and the submission has a material defect, EPA retains its right to seek stipulated penalties, as provided in Section XX (Stipulated Penalties).
39. Resubmission of Plans.
A. Upon receipt of a notice of disapproval pursuant to Paragraph 37(d), Settling Defendants shall, within 21 days or such longer time as specified by EPA in such notice, correct the deficiencies and resubmit the plan, report, or other item for approval. Any stipulated penalties applicable to the submission, as provided in Section XX, shall accrue during the 21 day period or otherwise specified period but shall not be payable unless the resubmission is disapproved or modified due to a material defect as provided in Paragraphs 40 and 41.
B. Notwithstanding the receipt of a notice of disapproval pursuant to Paragraph 37(d), Settling Defendants shall proceed, at the direction of EPA, to take any action required by any non-deficient portion of the submission. Implementation of any non-deficient portion of a submission shall not relieve Settling Defendants of any liability for stipulated penalties under Section XX (Stipulated Penalties).
40. In the event that a resubmitted plan, report or other item, or portion thereof, is disapproved by EPA, EPA may again require the Settling Defendants to correct the deficiencies, in accordance with the preceding Paragraphs. EPA also retains the right to modify or develop the plan, report or other item. Settling Defendants shall implement any such plan, report, or item as modified or developed by EPA, subject only to their right to invoke the procedures set forth in Section XIX (Dispute Resolution).
41. If upon resubmission, a plan, report, or item is disapproved or modified by EPA due to a material defect, Settling Defendants shall be deemed to have failed to submit such plan, report, or item timely and adequately unless the Settling Defendants invoke the dispute resolution procedures set forth in Section XIX (Dispute Resolution) and EPA's action is overturned pursuant to that Section. The provisions of Section XIX (Dispute Resolution) and Section XX (Stipulated Penalties) shall govern the implementation of the Work and accrual and payment of any stipulated penalties during Dispute Resolution. If EPA's disapproval or modification is upheld, stipulated penalties shall accrue for such violation from the date on which the initial submission was originally required, as provided in Section XX.
42. All plans, reports, and other items required to be submitted to EPA under this Consent Decree shall, upon approval or modification by EPA, be enforceable under this Consent Decree. In the event EPA approves or modifies a portion of a plan, report, or other item required to be submitted to EPA under this Consent Decree, the approved or modified portion shall be enforceable under this Consent Decree.
XII. PROJECT COORDINATORS
43. For the purposes of this Consent Decree, the following persons shall be the Project Coordinator/Alternate Coordinators for the Settling Defendants and EPA;
Settling Defendants Project Coordinator: David Williams, Technical Director, Ciba Specialty Chemicals Corporation North America, Oak Ridge Parkway, P.O. Box 71, Toms River, New Jersey 08754-0071.
EPA Project Coordinator: Romona Pezzella, Remedial Project Manager, U.S. Environmental Protection Agency, Emergency and Remedial Response Division, 290 Broadway, New York, NY 10007-1866.
EPA Alternate Project Coordinator: Don Lynch, Team Leader, U.S. Environmental Protection Agency, Emergency and Remedial Response Division, 290 Broadway, New York, NY 10007-1866.
Within 14 days of lodging this Consent Decree, Settling Defendants shall notify EPA, in writing, of the name, address and telephone number of their designated Alternate Project Coordinator. If a Project Coordinator or Alternate Project Coordinator initially designated is changed, the identity of the successor will be given to the other Parties at least 5 working days before the changes occur, unless impracticable, but in no event later than the actual day the change is made. The Settling Defendants' Project Coordinator or Alternate Coordinator shall be subject to disapproval by EPA and shall have the technical expertise sufficient to adequately oversee all aspects of the Work. The Settling Defendants' Project Coordinator shall not be an attorney for any of the Settling Defendants in this matter. He or she may assign other representatives, including other contractors, to serve as a Site representative for oversight of performance of daily operations during remedial activities.
44. Plaintiff may designate other representatives, including, but not limited to, EPA or State employees, and federal contractors and consultants, to observe and monitor the progress of any activity undertaken pursuant to this Consent Decree. EPA's Project Coordinator and Alternate Project Coordinator shall have the authority lawfully vested in a Remedial Project Manager (RPM) and an On-Scene Coordinator (OSC) by the National Contingency Plan, 40 C.F.R. Part 300. In addition, EPA's Project Coordinator or Alternate Project Coordinator shall have authority, consistent with the National Contingency Plan, to halt any Work required by this Consent Decree and to take any necessary response action when s/he determines that conditions at the Site constitute an emergency situation or may present an immediate threat to public health or welfare or the environment due to release or threatened release of Waste Material.
45. EPA's Project Coordinator and the Settling Defendants' Project Coordinator should endeavor to meet in person or by telephone on a monthly basis.
XIII. ASSURANCE OF ABILITY TO COMPLETE WORK
46. Within 30 days of entry of this Consent Decree, Settling Defendants shall establish and maintain financial security in the amount of $91,400,000 in one or more of the following forms:
A. A surety bond guaranteeing performance of the Work;
B. One or more irrevocable letters of credit equaling the total estimated cost of the Work;
C. A trust fund;
D. A guarantee to perform the Work by one or more parent corporations or subsidiaries, or by one or more unrelated corporations that have a substantial business relationship with at least one of the Settling Defendants; or,
E. A demonstration that the Settling Defendants satisfy the requirements of 40 C.F.R. Part 264.143(f) provided, however, that if EPA approves the assumption of the obligations of this Consent Decree by a new entity and that entity has not yet issued any bond, EPA shall accept an interim or "shadow" bond rating from a bond rating agency listed in the referenced regulations so long as the new entity otherwise meets the requirements of 40 C.F.R. Part 264.143(f) for the first year after such assumption of the obligations.
47. If the Settling Defendants seek to demonstrate the ability to complete the Work through a guarantee by a third party pursuant to Paragraph 46.d of this Consent Decree, Settling Defendants shall demonstrate that the guarantor satisfies the requirements of 40 C.F.R. Part 264.143(f) or Paragraph 46e. If Settling Defendants seek to demonstrate their ability to complete the Work by means of the financial test or the corporate guarantee pursuant to Paragraph 46.d or 46.e, they shall resubmit sworn statements conveying the information required by 40 C.F.R. Part 264.143(f) or pursuant to Paragraph 46e annually, by March 31 of each succeeding calendar year. In the event that EPA, determines at any time that the financial assurances provided pursuant to this Section are inadequate, Settling Defendants shall, within 30 days of receipt of notice of EPA's determination, obtain and present to EPA for approval one of the other forms of financial assurance listed in Paragraph 46 of this Consent Decree. Settling Defendants' inability to demonstrate financial ability to complete the Work shall not excuse performance of any activities required under this Consent Decree.
48. If Settling Defendants can show that the estimated cost to complete the remaining Work has diminished below the amount set forth in Paragraph 46 above after entry of this Consent Decree, Settling Defendants may, on any anniversary date of entry of this Consent Decree, or at any other time agreed to by the Parties, reduce the amount of the financial security provided under this Section to the estimated cost of the remaining work to be performed. Settling Defendants shall submit a proposal for such reduction to EPA, in accordance with the requirements of this Section, and may reduce the amount of the security upon approval by EPA. In the event of a dispute, Settling Defendants may reduce the amount of the security in accordance with the final administrative or judicial decision resolving the dispute.
49. Settling Defendants may change the form of financial assurance provided under this Section at any time, upon notice to and approval by EPA, provided that the new form of assurance meets the requirements of this Section. In the event of a dispute, Settling Defendants may change the form of the financial assurance only in accordance with the final administrative or judicial decision resolving the dispute.
XIV. CERTIFICATION OF COMPLETION
50. Completion of the Remedial Action.
A. Within 60 days after Settling Defendants conclude that the Remedial Action has been fully performed and the Performance Standards have been attained, Settling Defendants shall schedule and conduct a pre-certification inspection consistent with the terms of the attached SOW, to be attended by Settling Defendant and EPA. If, after the pre-certification inspection, the Settling Defendants still believe that the Remedial Action has been fully performed and the Performance Standards have been attained, they shall submit a Draft Remedial Action Report to EPA and the State requesting certification to EPA for approval, pursuant to Section XI (EPA Approval of Plans and Other Submissions) within 30 days of the inspection. In the report, a registered professional engineer and the Settling Defendants' Project Coordinator shall state that the Remedial Action has been completed in full satisfaction of the requirements of this Consent Decree. The written report shall include as-built drawings signed and stamped by a professional engineer. The report shall contain the following statement, signed by a responsible corporate official of a Settling Defendant or the Settling Defendants' Project Coordinator:
To the best of my knowledge, after thorough investigation, I certify that the information contained in or accompanying this submission is true, accurate and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations.
If, after completion of the pre-certification inspection and receipt and review of the Draft Remedial Action Report, EPA determines that the Remedial Action or any portion thereof has not been completed in accordance with this Consent Decree or that the Performance Standards have not been achieved, EPA will notify Settling Defendants in writing of the activities that must be undertaken by Settling Defendants pursuant to this Consent Decree to complete the Remedial Action and achieve the Performance Standards. Provided, however, that EPA may only require Settling Defendants to perform such activities pursuant to this Paragraph to the extent that such activities are consistent with the "scope of the remedy selected in the ROD," as that term is defined in Paragraph 14.b. EPA will set forth in the notice a schedule for performance of such activities consistent with the Consent Decree and the SOW or require the Settling Defendants to submit a schedule to EPA for approval pursuant to Section XI (EPA Approval of Plans and Other Submissions). Settling Defendants shall perform all activities described in the notice in accordance with the specifications and schedules established pursuant to this Paragraph, subject to their right to invoke the dispute resolution procedures set forth in Section XIX (Dispute Resolution).
B. If EPA concludes, based on the initial or any subsequent report requesting Certification of Completion that the Remedial Action has been performed in accordance with this Consent Decree and that the Performance Standards have been achieved, EPA will so certify in writing to Settling Defendants. This certification shall constitute the Certification of Completion of the Remedial Action for purposes of this Consent Decree, including, but not limited to, Section XXI (Covenants Not to Sue by Plaintiffs). Certification of Completion of the Remedial Action shall not affect Settling Defendants' obligations under this Consent Decree.
51. Completion of the Work.
A. Within 60 days after Settling Defendants conclude that all phases of the Work, have been fully performed, including long-term monitoring and maintenance, Settling Defendants shall schedule and conduct a pre-certification inspection consistent with the terms of the attached SOW, to be attended by Settling Defendants and EPA. If, after the pre-certification inspection, the Settling Defendants still believe that the Work has been fully performed, Settling Defendants shall submit a written report to EPA and the State by a registered professional engineer stating that the Work has been completed in full satisfaction of the requirements of this Consent Decree. The report shall contain the following statement, signed by a responsible corporate official of a Settling Defendant or the Settling Defendants' Project Coordinator:
To the best of my knowledge, after thorough investigation, I certify that the information contained in or accompanying this submission is true, accurate and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations.
If, after review of the written report, EPA determines that any portion of the Work has not been completed in accordance with this Consent Decree, EPA will notify Settling Defendants in writing of the activities that must be undertaken by Settling Defendants pursuant to this Consent Decree to complete the Work. Provided, however, that EPA may only require Settling Defendants to perform such activities pursuant to this Paragraph to the extent that such activities are consistent with the "scope of the remedy selected in the ROD," as that term is defined in Paragraph 14.b. EPA will set forth in the notice a schedule for performance of such activities consistent with the Consent Decree and the SOW or require the Settling Defendants to submit a schedule to EPA for approval pursuant to Section XI (EPA Approval of Plans and Other Submissions). Settling Defendants shall perform all activities described in the notice in accordance with the specifications and schedules established therein, subject to their right to invoke the dispute resolution procedures set forth in Section XIX (Dispute Resolution).
B. If EPA concludes, based on the initial or any subsequent request for Certification of Completion by Settling Defendants, that the Work has been performed in accordance with this Consent Decree, EPA will so notify the Settling Defendants in writing.
|